[!] 12JUN15 - 08:00AM : Scheduled NOC Power Outage - Start

posted Jun 12, 2015, 5:48 AM by Cash Keith   [ updated Jun 12, 2015, 5:49 AM ]
New electrical service is being turned on and added to our backup power array this morning Friday, June 12, 2015 beginning at 8:00am.  In order to make the connections and activate the service, the entire Network Operations and Data Center must have it's power shutdown.  The power maintenance window is expected to take 4 hours to complete, but we will also maximized this outage window to make some network cutovers once we have power restored.

This outage will mean no network or phones will be working while the electricity is shut off.